16 MTR April 2006 vessels
Merwede Shipyard received a contract for the design and construction of a new Pipe
Laying/Offshore Construction vessel for
Subsea 7. Delivery is scheduled for the sec- ond quarter of 2008. The pipe laying equip- ment will be designed and built by Huisman
Itrec. Subsea 7 said the overall project cost is estimated to be in the range of $170-200 million, depending on options exercised. The ship has been designed by Merwede Shipyard in close concert with Subsea 7 and the pipe- lay spread manufacturer. It will be designed and built to be a fully Dynamic Positioned
Pipe Laying/Offshore Construction Vessel, suitable for worldwide operation. Its pipe lay equipment will include a vertical lay system with top tension capability in excess of 400 tons, combined with a storage capacity for flexible pipe based on two 1,250-ton carousels below deck and a 3,000-ton carousel or multiple reels on deck. The vessel will have a 400 ton deepwater crane, a built- in deepwater ROV spread and a comprehen- sive survey system.
The vertical lay tower is also designed to enable operation in J-lay mode for rigid pipe and the ability to install large structures asso- ciated with deepwater riser systems. The ship will have a 6.6kV integrated electric power generation system and propulsion by three electromotor driven fixed pitch propellers in azimuthing nozzles aft. Two retractable
Azimuth thrusters will be fitted in the for- ward part of the vessel; one transverse thruster will be arranged in a tunnel forward.
The ship will be a fully Dynamic
Positioned Pipe Laying/Offshore
Construction Vessel, suitable for worldwide operation.
The vertical lay tower is also designed to enable operation in J-lay mode for rigid pipe and the ability to install large structures asso- ciated with deepwater riser systems.
Subsea 7 has options to have the vessel delivered with both of these capabilities fully operational.
Subsea 7 Orders Pipelay Vessel
Main Particulars
Length, o.a. . . . . . . . . . . . . . . . . . . . . . . . . .151 m
Length, bpp . . . . . . . . . . . . . . . . . . . . . . . .138.3 m
Breadth, molded 28.4 m
Depth, maindeck molded . . . . . . . . . . . . . . .12.5 m
Draft, design . . . . . . . . . . . . . . . . . . . . . . . . .7.5 m
Draft, scantling . . . . . . . . . . . . . . . . . . . . . . . . .8 m
Deadweight (w/Payload),scantling draft . .13,699 MT
Complement . . . . . . . . . . . . . . . . . . . . . . . . . .120
Classification . . . . . . . . .Lloyd's Register of Shipping
MTR#3 (1-16).qxd 4/7/2006 11:19 AM Page 18

15

17